Installation

The floor must be fully laid before installation, without skirting boards. Doors are installed already glazed, fixed panels are glazed on site. We install by inserting into the opening, the fixing holes are in the frame.

Anchoring is only possible into a floor on a single level. We do not recommend anchoring the pivot at a floor transition. It is better to align the outer edge of the door flush with the transition.

Around framed doors there is a gap of at least 2 mm for inserting into the opening, the same applies to fixed panels. If the opening is out of square, the gap will be uneven.

On request the gaps can be filled with white acrylic or sealant after installation.